Meet Olivia.
Olivia recently inherited a piece of property in La Union—a lot just a few minutes from the beach.
Follow along as she builds her dream life by the beach.
The Dream.
Every summer, she saw the tourist Industry boom and dreamed of putting up a three-storey commercial building there: cafés, surf shops, and rentals and her residence at the top floor.
She pictured herself earning passive income while keeping the property in the family.
The Problem.
But there was one thing holding her back:
Could she actually afford it?
Her Reality.
Olivia had:
₱5M in savings
₱10M loanable amount from her bank
That capped her total budget at ₱15M.
Starting the Journey.
Unsure of her next move, Olivia booked a co-creation workshop under Lateliér Incubator.
In just a few hours, she had zoning checks, sketches, and a first look at the possibilities—comparing potential revenue from different project directions.
Most importantly, she walked away with clarity and a sense that she finally had a roadmap.
TAP TO REVEAL HOW MUCH OLIVIA SPENT ON DESIGN FEES💰💸💵
3 hour Co-Creation Workshop
₱3,500 x 3 = ₱10,500.00
Testing the Dream.
The chemistry felt right, so she took the next step toward her project.
Then came Ideation—workshops exploring different layouts, materials, and financial strategies. Soon, Olivia was looking at schematic concepts she could visualize, test, and price.
TAP TO REVEAL HOW MUCH OLIVIA SPENT ON DESIGN FEES💰💸💵
4-hour Co-Creation Workshop
➜ ₱3,500 x 4 = ₱14,000.00
Phased Financial & Construction Planning
➜ ₱22.50 x 450 = ₱10,125.00
GRAND TOTAL
➜ ₱14,000 + ₱10,125 = ₱24,125.00
The Reality Check.
Here’s where things got tricky. The design Olivia loved was going to cost at least ₱20M to build.
With ₱15M available at most, she faced a hard truth: her dream project, as originally planned, was out of reach.
The Pivot.
But Olivia didn’t stop there. Together, we circled back to Ideation—this time with a sharper question:
What project would actually work within her ₱15M budget?
TAP TO REVEAL HOW MUCH OLIVIA SPENT ON DESIGN FEES💰💸💵
4-hour Co-Creation Workshop
➜ ₱3,500 x 4 = ₱14,000.00
Phased Financial & Construction Planning
➜ ₱21 x 450 = ₱9,450.00
GRAND TOTAL
➜ ₱14,000 + ₱9,450 = ₱23,450.00
New Strategy.
Instead of forcing the full three-storey commercial build, we explored phased development:
Phase 1: Generate Cashflow
Use her available funds to construct a single-storey row of shops at the front of the property, but with a foundation engineered for three storeys. This way, the structure could expand upward later without redoing the base. Once leased out, these shops were projected to generate at least ₱1M annually in rental income.
Phase 2: Reinvest into Expansion
Add the upper floors for rentals once Phase 1 was bringing in cashflow—and if needed, strengthen financing through a loan backed by her already-profitable asset.
TAP TO REVEAL HOW MUCH OLIVIA SPENT ON DESIGN FEES💰💸💵
4-hour Co-Creation Workshop
➜ ₱3,500 x 4 = ₱14,000.00
Phased Financial & Construction Planning
➜ ₱21 x 450 = ₱9,450.00
GRAND TOTAL
➜ ₱14,000 + ₱9,450 = ₱23,450
From Impossible to Feasible.
This strategy turned her project from impossible to achievable and income-generating giving a go signal to proceed to continue.
TAP TO REVEAL HOW MUCH OLIVIA SPENT ON DESIGN FEES💰💸💵
Exterior Schematic 3D Modelling
➜ ₱122.50 x 450 = ₱55,125.00
Building Forward.
Once the phased strategy was set, we created complete 3D models of the entire three-storey concept.
This helped Olivia see exactly how Phase 1—the ground-floor shops—would evolve into the full building over time.
TAP TO REVEAL HOW MUCH OLIVIA SPENT ON DESIGN FEES💰💸💵
Immersive 3D Modelling
➜ ₱90 x 450 = ₱40,500.00
Exterior Rendering
➜ ₱10,000 (Lump sum)
GRAND TOTAL
➜ ₱40,500 + ₱10,000 = ₱50,500.00
Getting into more detail.
With the vision in place, Olivia’s project advanced into the Technical Phase.
Here, we worked on detailed cost estimates, breaking the development into smaller, manageable phases.
Through cost optimization, we identified which specifications could be adjusted to reduce expenses without compromising the long-term vision.
At the same time, we helped Olivia secure a reputable contractor who was aligned with her budget and design goals—ensuring the project could move forward with confidence.
TAP TO REVEAL HOW MUCH OLIVIA SPENT ON DESIGN FEES💰💸💵
Environmental Impact Assessment (Pre-Requisite for an Environmental Compliance Certificate)
➜₱50,000 (Lump Sum)
Architectural Blueprints
➜₱700 x 450 = ₱315,000.00
Engineering Blueprints
➜₱630 x 450 = ₱283,500.00
Cost Estimates
➜₱22.5 x 450 = ₱10,125.00
Cost Optimization
➜₱22.5 x 450 = ₱10,125.00
Bill of Materials
➜₱22.5 x 450 = ₱10,125.00
Bill of Quantities
➜₱22.5 x 450 = ₱10,125.00
Timeline Management
➜₱22.5 x 450 = ₱10,125.00
Bid Assistance
➜₱22.5 x 450 = ₱10,125.00
GRAND TOTAL
➜₱50,000+ ₱315,000 + ₱283,500 + (₱10,125 x 6) = ₱709,250.00
Constructing the Dream.
Our team handled remote site management to oversee day-to-day progress.
At the same time, we scheduled monthly site visits to ensure that the plans were being followed down to the last detail.
TAP TO REVEAL HOW MUCH OLIVIA SPENT ON DESIGN FEES💰💸💵
Remote Site Monitoring (Monthly Retainer; 8 months)
₱10,000 x 8 = ₱80,000.00
Site Visit Fee